On Track

This is a way of indicating that you are progressing as expected and will finish the task in time. The % complete of the task will be automatically updated with the planned % complete value. E.g. if a task is 8 days long and at the end of the 2nd day you mark the task on track, the % complete of the task will be updated to 25%.