Importing Tasks from CSV

Celoxis provides you with the ability to import tasks in a project from CSV. If you have a Microsoft Excel file, then you can export it in CSV (comma separated values) format and then import it in Celoxis.

To import tasks in a project, first click on the project and then click Project ActionsMoreImport Tasks (CSV). Alternatively, if you are in the project Gantt chart, you can click AddImport CSV

Rules

Decimal NumberDo not use currency symbol or thousands separator. For example $10000.5 or 10,000.5 is not allowed. 10000.5 is allowed. BooleanSpecify either TRUE or FALSE. Empty text will be treated as FALSE. DateSpecify dates as YYYY-MM-DDThh:mm:ss E.g. 1994-11-05T08:15:30 corresponds to November 5, 1994, 8:15:30 am. You can also specify YYYY-MM-DD where time is not material. E.g. 2021-12-25 corresponds to 25th December 2021.

Fields

WBS CodeUse this to create the project's WBS (parent-child relationships). If we enter WBS codes as shown below on the left, you will get the task structure on the right. WBS CodeTask 1A 1.1B 1.2C 1.1.1D 1.1.2E 2F ► Project │ ├── A │ │ │ ├── B │ │ │ │ │ ├── D │ │ │ │ │ └── E │ │ │ └── C │ └── F
NameMandatory
Description
Planned StartDate
Planned FinishDate
Predecessors (WBS Codes)Semicolon separated WBS codes of predecessors
DurationEnter in the duration format described here.
Planned EffortDecimal number. Effort in hours.
ResourcesEnter resources in the format described here.
% DoneAn integer between 0 and 100.
Manually ScheduledBoolean
PriorityOne of VERY_HIGH, HIGH, NORMAL, LOW, or VERY_LOW
Schedule TypeOne of FIXED_WORK, FIXED_DURATION, or FIXED_UNITS
Constraint TypeOne of MSO, MFO, FNLT, SNLT, FNET, SNET, ASAP or ALAP. Read more.
Constraint DateDate
Actual StartDate
Actual FinishDate
BudgetDecimal number
FixedPriceDecimal number
Planned Fixed CostDecimal number
Planned Non-Labor CostDecimal number
Billing TypeFor No Billing, specify NONE, for Fixed Price specify FIXED_PRICE, and for Time & Material specify TNM
External KeyString. The key or id of this task in another system e.g. JIRA
Custom FieldsYou will have to create the fields in Celoxis first.

To read more about tasks dates,

.