You can create copies of a task in a recurring pattern of you choice.

  1. Open the interactive gantt in the project in which you want to create the recurring task.
  2. Create a task and name it appropriately e.g. Weekly Meeting.
  3. Right click on the task and click on Recur.
  4. Enter the desired recurrence pattern. In the following example, we have chosen a weekly pattern.
  5. Submit